Major Equipment Arrives at Amulsar


This week, Lydian International said major equipment components have arrived at its Amulsar gold project in Armenia. Major pieces of equipment for the crushing plant, including the jaw crusher, a secondary cone crusher, rock breaker, pan feeders, and screen liners have all arrived at the site. The material handling system includes crushing and screening equipment and the overland conveyor, all supplied by Sandvik. Components have been shipping since the second quarter of 2017 as fabrication is completed. Modular steel structures for the overland conveyer and other structural steel components are arriving on site and this will continue throughout the third quarter.

“Equipment lead times and delivery logistics present unique challenges for many projects,” said Howard Stevenson, Lydian’s president and CEO. “We are very pleased that our vendors are meeting fabrication schedules and deliveries to site are being well managed.”

Caterpillar remains on schedule in manufacturing the primary mine mobile equipment. The first phase of equipment, consisting of a 6040 hydraulic shovel, one CAT 994 front end loader, five 789D haul trucks and other equipment, was shipped in July. Deliveries to Amulsar and assembly are expected over the balance of the third quarter of 2017.

The gold recovery plant is being fabricated in South Africa by Azmet. Pre-assembled modules have been loaded for shipment later this month. Delivery is expected by late third-quarter 2017.

ABB is suppling all major site-wide electrical and control systems. Fabrication of the main substation and distribution grid, integrated automation and process control by optimized solutions, motors and drive systems is advancing in accordance with the manufacturer’s planned delivery schedules. Electrical transformers are scheduled for shipment this month, with delivery anticipated during the fourth quarter of 2017.


As featured in Womp 2017 Vol 09 - www.womp-int.com