E&MJ’s Annual Survey of Global Mining Investment
The mining boom continues—but signs of a slowdown appeared in 2007
By Magnus Ericsson and Viktoriya Larsson, Raw Materials Group


During 2007, 175 new mining investment projects with a total projected cost of US$58 billion were registered in Raw Materials Group’s Raw Materials Data Metals (RMD Metals) Mines/Projects database. This level of investment value is considerably higher than the $38 billion recorded in 2006. However, even though the dollar volume of projects has increased steadily since the trough of the mining cycle in 2002, when only 65 projects valued at $11 billion entered the global mining project pipeline, the number of new projects appears to have peaked in 2006, when more than 200 new listings appeared in the database.

Mining Investment Up 50%
By the end of 2007, the total sum of investment in the global mining industry’s project pipeline as recorded in the RMD Metals database was $308 billion, representing an increase of almost 50% over the figure recorded at the end of 2006—and a direct reflection of the continuing boom in the global mining industry. However, it should be noted that these year-end figures are not directly comparable from year to year, because it is impossible to ensure that all projects have been included. In other words, variations in project coverage influence the estimated volume and value of the project pipeline, and it is possible that a decline in the number of listed projects might be due to reduced coverage of the very smallest. Despite these procedural variations, RMG is still convinced that growth in the number of new projects has slowed.

Project capital cost estimates are updated throughout the year and with increasing demand for mining equipment, those costs are escalating quickly. However, we have also observed that projects are being expanded when moving from the feasibility to the construction phase and cost increases are thus not totally attributable to higher unit costs. During 2007, cost increases recorded for “old” projects—those first registered before the start of 2007—were of the same order of magnitude as newly registered projects, or about $50 billion when projects that have been completed during the year are also taken into account. This is partly due to increased costs for equipment but also to development of more complex ore bodies; deeper, lower grade deposits; and the increasingly remote locations of new mines. The demand for experienced staff has also turned out to be a bottleneck in areas such as Western Australia where investment activity is running in top gear and has been doing so for some time. All these observations together indicate a rising long-term cost level beneath the soaring metal prices.

30% Increase in Value of Projects Under Construction
More projects than ever before have been given the green light and the survey’s Construction category has consequently expanded in 2007 for the fifth consecutive year. Currently listed are projects under construction valued at a total of $31 billion worldwide, up from $23 billion in 2006 and representing an increase of more than 30%. It should be pointed out that many projects, brownfield types in particular as well as those carried out by major transnational mining companies and by smaller locally owned companies, are never publicly announced and do not appear in the database. Thus, the investment figure for projects under construction is quite likely an under-estimate for this category.

Investment in brownfield projects totals $75 billion in this year’s database, up slightly in relative terms from last year. A project usually takes more than a year to realize (on average 12-18 months) depending on the location, available infrastructure, availability of financing and many other factors. The volume of projects in pre-feasibility stages has grown, indicating that there is still a steady flow of new projects into the pipeline. Our earlier prediction that there will be a continued growth in projects under construction at least in the next year seems to be correct but with the first signs of a slowdown in metal price increases—and with some prices actually dropping—we estimate growth in 2008 will be slower than in 2007.

All statistics are based on projects with a recorded projected investment. The RMD Metals Mines/Projects database also includes more than 1,900 projects for which no investment estimates are available. The database also includes 350 projects at the pre-feasibility and feasibility stages. The investment total for all mining projects, including those projects for which no investment estimate has been published, is much higher than $308 billion, but it is difficult to estimate how much higher. The total figure would probably reach well above $500 billion if it is assumed that projects without published investment estimates have a similar cost structure to projects whose costs are known. It could, however, also be argued that the remaining projects are less expensive, because most mega-projects are conducted by public companies that must disclose all important investment to the public. If this is the case, the total figure would be smaller.

Metals not covered in this report but included in the database, such as bauxite and some alloying metals, also require additional investment. Had they also been included, the total figure would increase further but probably by not more than $20 to $25 billion cumulatively at the mine stage.

The Big Four Grab 82%
Copper, iron ore, gold and nickel, respectively, are the major investment targets for mining companies. These four metals account for 82% of the total project pipeline. They also dominate the industry in terms of the total value of its output, being cumulatively valued at $235 billion or 63% of the total value of all non-fuel minerals production.


Continued high demand and healthy increases in prices paid have made iron ore one of the hottest investment targets. Of the total amount of investments into new projects presented in 2007 almost 50% are iron ore projects, up dramatically from 2006 both in relative and absolute terms. This level of spending caused iron ore to jump from fourth place to recapture second place in the overall ranking, almost catching up with copper.

Gold and nickel’s respective shares of the total pipeline dropped, while copper remained at the same level as in 2006. The database’s “Other” category increased slightly, mostly from new uranium, molybdenum and other ferroalloys projects. Interest in PGMs fell, and lead/zinc’s portion of total proposed investment remained static after a strong increase in 2006.

Although the average cost of a gold project has risen to about $130 million, it is still much lower than the $345-millionplus average cost for copper projects. This is because it is still possible to find small, high-grade gold deposits that can be mined profitably by junior or mid-sized companies, while most new copper projects are often huge low-grade surface operations.

The average iron ore project is even costlier than a copper project, reaching well above $500 million. Nickel projects once were the largest of all types, with new laterite technologies being technically more demanding and the ore grades often low, necessitating haulage of large volumes of ore and waste, but iron ore projects are catching up fast. PGM project costs fall in between those of copper and gold projects, while zinc project costs are generally in the same range as gold projects.

When comparing average costs over the last couple of years, price increases become obvious: Gold project costs, for example, have almost doubled. But it also appears that this rapid rate of increase has slowed somewhat, as average prices for new projects did not increase significantly in 2007 when compared with the total average over all years.

Among the new projects listed in the database during 2007, iron ore dominates accounting for over 47% of the value of all new projects. Copper follows with 27%. Gold, at 7%, declined markedly from 17% in 2006. Nickel’s 8% is also half of its level in the previous year.

Latin America has been a focus for mining investors of the world for several years, and slightly less than a third of this year’s listed projects are located in Latin American countries. In 2007, Latin America’s share of project investment increased after two years of decline. Oceania, including Australia and Papua New Guinea, remains the second most important region with about 20% of the investment pipeline. Africa’s share remained static during 2007, while North America’s grew from 13% to 15% due mainly to an increase in projects in Canada. Asia’s share of investments dropped from 14% to 11% in spite of an absolute increase of $6 billion. Europe drew 8% of global investment, roughly the same level as last year.

Spreading the Dollars
In 2007, 10 nations attracted 61% of total investments. This is a major reduction in cumulative share from 2006, indicating that mining investments are being spread more evenly around the globe; simply, the race for resources has been extended to more countries than before. Australia, still uncontested at the top with $45 billion in its pipeline, remains the most attractive country for mining investments ranging from huge iron ore projects in Western Australia to base metals and numerous gold projects continent-wide. Canada remains in second place increasing its share to 11%. Brazil is third, having expanded its project pipeline by over 100% due mainly to the giant iron ore projects planned in several parts of the country. Chile follows in fourth, down from third in 2006 and second in 2005, with a portfolio of $23 billion account representing 7% of total investment. South Africa fell to fifth. Peru remained in sixth, further establishing it as a stable, important mining nation. Russia’s move up the list has ended, with both its position and its share of total investments remaining static in 2007 after several years of growth, perhaps reflecting increasing uncertainty about future control over natural resources in the country.

Below the top-10 cutoff are New Caledonia, Argentina, DRC, Papua New Guinea, Mongolia, Madagascar, China and Kazakhstan, in that order, each with a portfolio of projects valued at between $3 billion and $7 billion. However, this range probably represents a sigificant under-estimate of mining investment in China.





As featured in Womp 08 Vol 1 - www.womp-int.com